Renewable Colocation for Waste Management Site
Project
|
Colocation for Waste Management Site |
Location |
Edmonton, North London, UK |
Industry |
Commercial and Industrial |
Application |
Energy Cost Reduction |
Brief |
To build and supply a single 80kW/338 KWh battery solution. The battery will be used for storing energy created from local AC coupled solar PV and used to supply power during ‘dark hours’. MSP to provide control system to integrate with local site controller.
A single GRP IP64 enclosure will house the suite of batteries, inverter, HVAC and controller(s). This unit was to be sited on the 1st floor and needed to be lifted by crane over 16m.
|
Specification |
|